70 per cent of the work of Ram’s Garbhgrah temple was completed in Ayodhya. – Ayodhya: 70 percent of the work of the Mahapeeth of the sanctum sanctorum has been completed, from January 2024, devotees will begin to receive the darshan of Lord Shri Ram

listen to the news

Construction work on the Ram temple is underway at the Ramjanmabhoomi complex. To date, 35 percent of the works on the Ram temple and 70 percent of Mahapeeth’s works on the sanctum sanctorum have been completed. The Ramlala shrine, plinth and retaining wall are being built simultaneously. The work of shaping the Mahapeeth takes place first in the sanctum sanctorum. Ramlala will sit on the seven-foot-tall Mahapeeth which will be built in five layers. The work of the third layer has reached the final phase. 80 stones have been laid. Shri Ram Janmabhoomi Teerth Kshetra Trust says that from January 2024, devotees will start receiving Ramlala’s darshan in the great shrine.

The place where the Lord dwells is called Mahapeeth. Chief Minister Yogi Adityanath had begun construction of the Mahapeeth of the sanctum sanctorum by offering prayers. It has been 45 days since the start of their works, so far 70 per cent of the works have been completed. The work of shaping the five-layer Mahapeeth is underway, so far three layers are almost finished. When a maximum of 49 stones were placed on the first layer, different numbers of stones were placed on the second and third layers. In this way, a total of 80 stones have been placed in the Mahapeeth.

After the completion of the Mahapeeth, work will begin on raising the pillars. All the pillars on the first floor of the temple are ready. The interior and floor of the sanctum sanctorum of the temple will be decorated with Makrana marble. Various carvings have been made in the stones. In the stones of the first layer, deities have been represented, in the second layer flowers and leaves and auspicious signs, elephants in the third layer, many dimensions of horses in the fourth and various shapes have been marked in the stones. of the fifth. cover.

The 30-foot-wide parikrama path is also taking shape
On the other hand, the work of 70 percent of the plinth of the temple of Ram has also been completed. In this one, 17 thousand granite stones must be used. So far about 11,000 stones have been installed while 15,000 granites have been supplied. In parallel, the construction of the sanctuary’s circumambulation is also underway. As the work on the plinth progresses, the circumambulation path will also take shape. The parikrama path will be about 30 feet wide. At the same time, work on the retaining wall up to a height of six meters has also been completed. To protect the temple from natural calamities, a 12-meter-deep retaining wall is being built.

Meeting of the temple construction committee from 20
The Ram Mandir Construction Committee meeting to be held each month will begin on July 20th. A joint meeting of the Ram Mandir Construction Committee and Shri Ram Janmabhoomi Teerth Kshetra Trust is organized every month. In this, along with the review of the progress of the construction of the Ram temple, future plans are discussed. Nripendra Mishra, chairman of the temple construction committee, including trusted officials, members and engineers also attended the meeting.

Dr. Anil Mishra, a member of Shri Ram Janmabhoomi Teerth Kshetra Trust, says the design of the pilgrimage center is being prepared for Parkota and 25,000 devotees. Our goal is that from January 2024, Ramlala’s darshan can be accessible to devotees of the great shrine.

Expansion

Construction work on the Ram temple is underway at the Ramjanmabhoomi complex. To date, 35 percent of the works on the Ram temple and 70 percent of Mahapeeth’s works on the sanctum sanctorum have been completed. The Ramlala shrine, plinth and retaining wall are being built simultaneously. The work of shaping the Mahapeeth takes place first in the sanctum sanctorum. Ramlala will sit on the seven-foot-tall Mahapeeth which will be built in five layers. The work of the third layer has reached the final phase. 80 stones have been laid. Shri Ram Janmabhoomi Teerth Kshetra Trust says that from January 2024, devotees will start receiving Ramlala’s darshan in the great shrine.

The place where the Lord dwells is called Mahapeeth. Chief Minister Yogi Adityanath had begun construction of the Mahapeeth of the sanctum sanctorum by offering prayers. It has been 45 days since the start of their works, so far 70 per cent of the works have been completed. The work of shaping the five-layer Mahapeeth is underway, so far three layers are almost finished. When a maximum of 49 stones were placed on the first layer, different numbers of stones were placed on the second and third layers. In this way, a total of 80 stones have been placed in the Mahapeeth.

After the completion of the Mahapeeth, work will begin on raising the pillars. All the pillars on the first floor of the temple are ready. The interior and floor of the sanctum sanctorum of the temple will be decorated with Makrana marble. Various carvings have been made in the stones. In the stones of the first layer, deities have been represented, in the second layer flowers and leaves and auspicious signs, elephants in the third layer, many dimensions of horses in the fourth and various shapes have been marked in the stones. of the fifth. cover.

The 30-foot-wide parikrama path is also taking shape

On the other hand, the work of 70 percent of the plinth of the temple of Ram has also been completed. In this one, 17 thousand granite stones must be used. So far about 11,000 stones have been installed while 15,000 granites have been supplied. In parallel, the construction of the sanctuary’s circumambulation is also underway. As the work on the plinth progresses, the circumambulation path will also take shape. The parikrama path will be about 30 feet wide. At the same time, work on the retaining wall up to a height of six meters has also been completed. To protect the temple from natural calamities, a 12-meter-deep retaining wall is being built.

Meeting of the temple construction committee from 20

The Ram Mandir Construction Committee meeting to be held each month will begin on July 20th. A joint meeting of the Ram Mandir Construction Committee and Shri Ram Janmabhoomi Teerth Kshetra Trust is organized every month. In this, along with the review of the progress of the construction of the Ram temple, future plans are discussed. Nripendra Mishra, chairman of the temple construction committee, including trusted officials, members and engineers also attended the meeting.

Dr. Anil Mishra, a member of Shri Ram Janmabhoomi Teerth Kshetra Trust, says the design of the pilgrimage center is being prepared for Parkota and 25,000 devotees. Our goal is that from January 2024, Ramlala’s darshan can be accessible to devotees of the great shrine.

Leave a Comment