Unused cash, arrears, negligent indebtedness Karnal

listen to the news

Gagan Talwar
Carnival. The state treasury is open to do small works related to the people of the city, but due to the negligence and tardiness of the officials, this treasury was not used in time. As a result, the budget expired and Karnal went into debt due to the delay in the work. It will now have an impact on growth this year. That is why the public will have to bear the brunt of the problems.
It so happened that under plan D, the government released 21.66 million rupees for the development of the district in 2021-22. Therefore, the administration started 486 works once planned. After these works were completed on March 31, 2022, their bills were to be approved, but department officials were only able to deposit up to Rs 9.50 crore. In this case, the remaining 12.16 million rupees has expired. Although works worth 11.52 million rupees were also done with this expired amount, but their bills were not approved in time.
Now this amount will have to be paid by the administration with the newly published 23.75 million rupees for the financial year 2022-23. In this situation, even after getting 2.08 million rupees more from the government than last time this year, the development work will be done with only 12.22 million rupees. According to last year’s report, out of a total of 486 works, the negligence of the Municipal Corporation and the Panchayati Raj Department has been the highest. The maximum amount was allocated and the work, of the amount due, in these two departments are pending invoices of about six million. Office
Last year there was no liability, this time up 11.52 million
In 2020-21, all D-Plan works were completed by officials on time. Whatever the budget was spent. In this situation, there was no responsibility for that year in the 2021-22 budget. The government had instructed to do the development work with the entire budget of Rs 21.66 crore. The money was not spent full time, so this year, i.e. 2022-23, there is a liability of Rs 11.52 crore on the budget of Rs 23.75 crore.
These are the works of plan D.
70 per cent of the amount goes to works of primary needs of the public, such as renovation of schools, community centers, chaupals, water supply, Anganwadi centers, nursing homes and construction of toilets.
– 30 percent of the amount goes to the construction of roads, streets and drains, sewers.
The budget is published according to the need and population of the eight blocks and municipal bodies. The total population of the district is 15 lakhs.
This is the position (amount in lakhs)
Year 2021-22 –
Total budget released 2166.90
Bill passed 950.43
expired 1216.47
(There was no responsibility for the works carried out during the year 2020-21.)
,
Year 2022-23 –
Total published budget 2375.14
1222.36 will be spent on works
(There is a liability of 11.52 million works completed in 2021-22).
Bills from the Municipal Corporation and Panchayati Raj Department were left pending. Due to their negligence, they will be given less work and budget in this budget. Of the total amount released under Plan D, the first works carried out for the last 11.52 million rupees will be paid. New works will be made from the remaining amount.
– Dr. Vaishali Sharma, ADC

Gagan Talwar

Carnival. The state treasury is open to do small works related to the people of the city, but due to the negligence and tardiness of the officials, this treasury was not used in time. As a result, the budget expired and Karnal went into debt due to the delay in the work. It will now have an impact on growth this year. That is why the public will have to bear the brunt of the problems.

It so happened that under plan D, the government released 21.66 million rupees for the development of the district in 2021-22. Therefore, the administration started 486 works once planned. After these works were completed on March 31, 2022, their bills were to be approved, but department officials were only able to deposit up to Rs 9.50 crore. In this case, the remaining 12.16 million rupees has expired. Although works worth 11.52 million rupees were also done with this expired amount, but their bills were not approved in time.

Now this amount will have to be paid by the administration with the newly published 23.75 million rupees for the financial year 2022-23. In this situation, even after getting 2.08 million rupees more from the government than last time this year, the development work will be done with only 12.22 million rupees. According to last year’s report, out of a total of 486 works, the negligence of the Municipal Corporation and the Panchayati Raj Department has been the highest. The maximum amount was allocated and the work, of the amount due, in these two departments are pending invoices of about six million. Office

Last year there was no liability, this time up 11.52 million

In 2020-21, all D-Plan works were completed by officials on time. Whatever the budget was spent. In this situation, there was no responsibility for that year in the 2021-22 budget. The government had instructed to do the development work with the entire budget of Rs 21.66 crore. The money was not spent full time, so this year, i.e. 2022-23, there is a liability of Rs 11.52 crore on the budget of Rs 23.75 crore.

These are the works of plan D.

70 per cent of the amount goes to works of primary needs of the public, such as renovation of schools, community centers, chaupals, water supply, Anganwadi centers, nursing homes and construction of toilets.

– 30 percent of the amount goes to the construction of roads, streets and drains, sewers.

The budget is published according to the need and population of the eight blocks and municipal bodies. The total population of the district is 15 lakhs.

This is the position (amount in lakhs)

Year 2021-22 –

Total budget released 2166.90

Bill passed 950.43

expired 1216.47

(There was no responsibility for the works carried out during the year 2020-21.)

,

Year 2022-23 –

Total published budget 2375.14

1222.36 will be spent on works

(There is a liability of 11.52 million works completed in 2021-22).

Bills from the Municipal Corporation and Panchayati Raj Department were left pending. Due to their negligence, they will be given less work and budget in this budget. Of the total amount released under Plan D, the first works carried out for the last 11.52 million rupees will be paid. From the remaining amount, new works will be carried out.

– Dr. Vaishali Sharma, ADC