Fraud, Investigate, Team, Village

listen to the news

Tarabganj (Gonda). The issue of grabbing the budget of lakhs without doing the work in the Gram Panchayat Bangaon of the block has caught fire. A complaint has been lodged with the DM and the CDO, including the Commissioner, in this case, after which a two-member team has been constituted for investigation.
Pankaj Singh, a resident of Bangaon, said in the complaint that the development works carried out during the last financial year were limited to paper only, while the money was wasted. He said that money withdrawn on various items like construction of Khandja and RCC road, construction of disabled toilets, maintenance of community toilets, hand pump rebars have been taken showing paper work. During the floods, the amount of four boats which were to be purchased for the convenience of the people was also fraudulently withdrawn. Taking cognizance of the complaint received against the village head and clerk in this regard, the district magistrate has constituted a two-member investigation team and called for the investigation report.
Deputy Director Silk and Executive Engineer Saryu Canal Section-4 have been included in the investigation team. Village headman Manjit Singh says the estimate is earlier. The works were stopped due to lack of manpower. Now workers have been found, on whom work has begun. BDO in-charge Ambareesh Singh said the construction work has stopped. It is being investigated.
The work started from the knowledge of the research
As soon as the investigation has come to the knowledge of the head of the affected village and the secretary, they have begun to complete the works without finishing in a hurry. Whistleblower Pankaj Singh has filed a complaint in public hearing along with a tweet to senior officials on Thursday. He said the culprits, frightened by the investigation, started speeding up the construction of the RCC road on Wednesday to prove their innocence, while their money was withdrawn years ago.
The complainant is a victim of anger
Complaints about irregularities in development works sometimes go unnoticed by representatives. That is why the accusers must fall in their anger. In the past, a complaint was lodged at Gram Panchayat Chandipur Development Works Block in Tarabganj for ignoring the rules. He was accused of having done the ground work without the financial approval and the call. The official alleges that the senior representative, upset by the complaint, misled the woman’s boss and filed a false case. In which there is a war of supremacy between the employment officer and the head of the organization regarding the registered case. (Dialogue)

Tarabganj (Gonda). The issue of grabbing the budget of lakhs without doing the work in the Gram Panchayat Bangaon of the block has caught fire. A complaint has been lodged with the DM and the CDO, including the Commissioner, in this case, after which a two-member team has been constituted for investigation.

Pankaj Singh, a resident of Bangaon, said in the complaint that the development works carried out during the last financial year were limited to paper only, while the money was wasted. He said that money withdrawn on various items like construction of Khandja and RCC road, construction of disabled toilets, maintenance of community toilets, hand pump rebars have been taken showing paper work. During the floods, the amount of four boats which were to be purchased for the convenience of the people was also fraudulently withdrawn. Taking cognizance of the complaint received against the village head and clerk in this regard, the district magistrate has constituted a two-member investigation team and called for the investigation report.

Deputy Director Silk and Executive Engineer Saryu Canal Section-4 have been included in the investigation team. Village headman Manjit Singh says the estimate is earlier. The works were stopped due to lack of manpower. Now workers have been found, on whom work has begun. BDO in-charge Ambareesh Singh said the construction work has stopped. It is being investigated.

The work started from the knowledge of the research

As soon as the investigation has come to the knowledge of the head of the affected village and the secretary, they have begun to complete the works without finishing in a hurry. Whistleblower Pankaj Singh has filed a complaint in public hearing along with a tweet to senior officials on Thursday. He said the culprits, frightened by the investigation, started speeding up the construction of the RCC road on Wednesday to prove their innocence, while their money was withdrawn years ago.

The complainant is a victim of anger

Complaints about irregularities in development works sometimes go unnoticed by representatives. That is why the accusers must fall in their anger. In the past, a complaint was lodged at Gram Panchayat Chandipur Development Works Block in Tarabganj for ignoring the rules. He was accused of having done the ground work without the financial approval and the call. The official alleges that the senior representative, upset by the complaint, misled the woman’s boss and filed a false case. In which there is a war of supremacy between the employment officer and the head of the organization regarding the registered case. (Dialogue)

Leave a Comment